142 Ellert St
San Francisco permit 202106071790 · Bernal Heights
Addition of one (1) accsessory dwelling units to an existing rear yard structure per government code section 65852.2.the proposed adu is located at the first floor within the existing envelope of the rear structure.
- Filed
- Jun 7, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 20 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Jun 7, 2021 | Jun 15, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 15, 2021 | Dec 8, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 15, 2021 | Dec 9, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2021 | Jun 17, 2021 | — |
Urban forestry Public Works · DPW-BUF | Jun 15, 2021 | Dec 27, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 15, 2021 | Jul 23, 2021 | — |
Development fee collection Building Inspection · DFCU | Jun 15, 2021 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2021 | Dec 16, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2021 | Dec 27, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2022 | Jan 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2022 | Jan 25, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2022 | Mar 2, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 4, 2022 | Jan 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 4, 2022 | Mar 4, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 4, 2022 | Mar 7, 2022 | — |
Planning review Planning · CP-GEN | Jun 10, 2022 | Jul 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 28, 2022 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2025 | Jan 21, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $51,900
| Name | Role | License on permit |
|---|---|---|
| J Mastro | Architect | C-35515 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025