97 Saturn St
San Francisco permit 202106142323 · Castro/Upper Market
New foundation; create (n) habitable space @ lower level crawl space; new stairs to connect 1st floor with lower level; remodel kitchen, 3 new bedrooms, 2 new bathrooms, 1 laundry room
- Filed
- Jun 14, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 13 stops across 4 departments
- Comments issued
- None
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jun 14, 2021 | Jun 14, 2021 | — |
Intake Building Inspection · INTAKE | Jun 14, 2021 | Jun 14, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2021 | Jun 21, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Mar 2, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2021 | Oct 26, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 3, 2021 | Nov 30, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2021 | May 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2021 | Oct 19, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 30, 2021 | Nov 30, 2021 | — |
Fire prevention review Fire Department · SFFD | Feb 17, 2022 | Feb 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2022 | Mar 30, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 6, 2022 | May 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 6, 2022 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $175,000
| Name | Role | License on permit |
|---|---|---|
| Jay Sherlock Studio J. Architecture | Architect | C33354 |
| Seri Ngernwattana Seri Ngerwattana, Pe | Engineer | C66949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023