Horizontal addition at rear yard addition

Timeline
Key dates from the city record.
Filed
Jun 14, 2021
Issued
Feb 27, 2024 (32 months after filing)
Completed
Nov 12, 2024 (9 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 3 departments
Comments issued
7 times, by Building Inspection
Put on hold
Twice
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Jun 14, 2021—

Zoning review

Planning · CP-ZOC

Jul 26, 2022—

Planning neighborhood notice

Planning · CP-NP

Oct 18, 2022—

Permit Center

Permit Center · PERMIT-CTR

Oct 19, 2022—

Building plan review

Building Inspection · BLDG

Dec 30, 2022—

Intake

Building Inspection · INTAKE

May 23, 2023—

Zoning review

Planning · CP-ZOC

May 23, 2023—

Central Permit Bureau

Building Inspection · CPB

May 23, 2023—

Building plan review

Building Inspection · BLDG

Sep 20, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 20, 2023Issued Comments

Permit Center

Permit Center · PERMIT-CTR

May 23, 2023—

Central Permit Bureau

Building Inspection · CPB

Oct 24, 2023Administrative

Building plan review

Building Inspection · BLDG

Nov 2, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 2, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 6, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Dec 14, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Feb 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 6, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 6, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 7, 2024Approved

Zoning review

Planning · CP-ZOC

Feb 16, 2024Approved

Permit Processing Center

Building Inspection · PPC

Feb 20, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Feb 27, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$110,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Cecil W Swason

C. Swason

ArchitectC-8991
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202106142354 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record