1380 A Chestnut St
San Francisco permit 202106142387 · Marina
New unit under density at level 1. change use from r-3 to r-2.seismic strengthening at level 1. fire sprinklers at level 1 (deferred). manual fire alram at all units (deferred).
- Filed
- Jun 14, 2021
- Issued
- Aug 8, 2023 (26 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 5 departments
- Comments issued
- None
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Jun 14, 2021 | Jun 25, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 25, 2021 | Jul 7, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 25, 2021 | May 10, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2021 | Dec 30, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 25, 2021 | Jul 6, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2021 | Jul 8, 2021 | — |
Urban forestry Public Works · DPW-BUF | Jun 25, 2021 | May 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2021 | Jul 26, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jul 28, 2022 | Aug 7, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 30, 2022 | Aug 1, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 30, 2022 | Jan 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2022 | Dec 30, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 9, 2023 | May 9, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 9, 2023 | May 11, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2023 | Jul 3, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 28, 2023 | Jun 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2023 | Jun 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2023 | Jun 29, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 28, 2023 | Jun 28, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Aug 7, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2023 | Aug 8, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Andrea Gabriele Cernusak Andrea Cernusak Architect | Architect | C-33206 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025