288 Union St #0
San Francisco permit 202106152475 · North Beach
Project consists of converting (e) 1st floor area of (e) 4 story multifamily building (3 dwelling units) into an adu (of 607 sq ft, 1 bedroom, 1 bath). work limited to non-structural fixtures only. no changes to existing structural foundation/framing, building footprint or exterior proposed.
- Filed
- Jun 15, 2021
- Issued
- Jan 25, 2023 (19 months after filing)
- Completed
- Nov 20, 2023 (10 months after issuance)
- Review stops
- 27 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Jun 15, 2021 | Jun 23, 2021 | — |
Building inspector Building Inspection · BID-INSP | Jun 23, 2021 | Jun 24, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 23, 2021 | Aug 26, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2021 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2021 | Dec 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2021 | Dec 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 23, 2021 | Jan 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2021 | Jun 28, 2021 | — |
Urban forestry Public Works · DPW-BUF | Jun 23, 2021 | Aug 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2021 | Jul 21, 2021 | — |
Development fee collection Building Inspection · DFCU | Jun 23, 2021 | Jan 12, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 31, 2021 | Aug 31, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2022 | Aug 1, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2022 | Jul 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 28, 2022 | Jan 19, 2023 | — |
Zoning review Planning · CP-ZOC | Sep 20, 2022 | Oct 5, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2022 | Sep 22, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2022 | Sep 21, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 2, 2022 | Nov 15, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 2, 2022 | Nov 3, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2022 | Nov 4, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 5, 2022 | Dec 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2022 | Dec 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2022 | Dec 7, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2022 | Dec 9, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Jan 19, 2023 | Jan 19, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 19, 2023 | Jan 25, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $90,000
| Name | Role | License on permit |
|---|---|---|
| Yogesh Chitlangia Aadiarch Inc | Architect | C-31132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026