711 Eddy St
San Francisco permit 202106152499 · Tenderloin
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa #201808086727 due to changes in the associated permit changes in the field.
- Filed
- Jun 15, 2021
- Issued
- Aug 12, 2022 (14 months after filing)
- Completed
- Jan 26, 2023 (5 months after issuance)
- Review stops
- 33 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 16, 2021 | Jun 17, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 17, 2021 | Aug 9, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 18, 2021 | Sep 9, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2021 | Jul 22, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2021 | Oct 15, 2021 | — |
Fire prevention review Fire Department · SFFD | Jul 20, 2021 | May 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2021 | Aug 12, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2021 | Dec 14, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 28, 2021 | Jul 28, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 28, 2021 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 16, 2021 | Sep 1, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 16, 2021 | Oct 21, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Aug 23, 2021 | Jul 6, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2021 | Oct 25, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 27, 2021 | Oct 21, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 13, 2021 | Dec 14, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 13, 2021 | Dec 14, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 13, 2021 | Dec 14, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 17, 2022 | Jul 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2022 | Jun 17, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2022 | Jun 17, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 17, 2022 | Jun 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2022 | Jul 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2022 | Jul 14, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Aug 1, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 28, 2022 | Jul 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2022 | Jul 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jul 28, 2022 | Jul 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 28, 2022 | Aug 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2022 | Aug 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2022 | Jul 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2022 | Aug 12, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Aug 12, 2022 | Aug 12, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| William Stuart Lyle Sgpa Arch & Planning | Architect | C24741 |
| Kevin Gerald Morton Hohbach-Lewin Inc. | Engineer | S-5181 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026