1 Bush St #0
San Francisco permit 202106172714 · Financial District/South Beach
14th fl restroom remodel. remodel all finishes except floors and install new finishes, plumbing fixtures and partitions.
- Filed
- Jun 17, 2021
- Issued
- Aug 27, 2021 (2 months after filing)
- Completed
- Mar 24, 2022 (7 months after issuance)
- Review stops
- 7 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 17, 2021 | Jun 17, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 21, 2021 | Jun 21, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Jun 21, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 21, 2021 | Jun 21, 2021 | — |
Fire prevention review Fire Department · SFFD | Jun 21, 2021 | Jun 21, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2021 | Aug 24, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2021 | Aug 27, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Steven Perry Perry Architectus, Inc. | Architect | C26289 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025