1765 California St
San Francisco permit 202106212853 · Western Addition
T.i for (e) whole foods. interior metal stud framing, interior concrete slab modifications for utility piping and conduit, interior finishes, new/relocated equipment, lighting, hvac, updates to sales flr, offices, and basement team member lounge.
- Filed
- Jun 21, 2021
- Issued
- Dec 16, 2021 (6 months after filing)
- Completed
- Mar 21, 2023 (15 months after issuance)
- Review stops
- 16 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 21, 2021 | Jun 21, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Aug 24, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 21, 2021 | Jun 21, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Jul 13, 2021 | Jul 13, 2021 | — |
Fire prevention review Fire Department · SFFD | Jul 13, 2021 | Jul 13, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2021 | Jul 13, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 14, 2021 | Jul 14, 2021 | — |
Public health review Public Health · HEALTH | Jul 14, 2021 | Aug 3, 2021 | — |
Public health review Public Health · HEALTH | Aug 24, 2021 | Aug 24, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2021 | Sep 1, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 22, 2021 | Sep 22, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Sep 22, 2021 | Sep 22, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2021 | Sep 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2021 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 16, 2021 | Dec 16, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 16, 2021 | Dec 16, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $990,000
| Name | Role | License on permit |
|---|---|---|
| Mariah B Meyer | Architect | c37440 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2017