1013 Castro St
San Francisco permit 202107013554 · Noe Valley
New kitchen, powder rm, office, stair on 2nd floor. new bedroom & closet on 3rd floor. raise plate hts & flatten back appro 14'-5" portion of (e) rear gable roof. new flat roof & parapet to be no higher than (e) roof ridge. not visible from street. new rear facing windows on raised back portion of
- Filed
- Jul 1, 2021
- Issued
- May 12, 2022 (10 months after filing)
- Completed
- Aug 14, 2024 (27 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 2, 2021 | Jul 2, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 2, 2021 | Jan 5, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Nov 2, 2021 | Nov 5, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 5, 2022 | Apr 20, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2022 | Apr 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2022 | May 4, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 5, 2022 | May 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 5, 2022 | May 12, 2022 | — |
Addendum 1: Arch,struct,t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 13, 2022 | May 13, 2022 | — |
Building plan review Building Inspection · BLDG | May 13, 2022 | Nov 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2022 | Jan 26, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 9, 2022 | Dec 1, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 17, 2022 | Nov 21, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 26, 2023 | Jan 26, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 26, 2023 | Jan 27, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| George A Wesely 2v Design | Architect | C28132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022