1 V Castenada Av
San Francisco permit 202107013600 · West of Twin Peaks
Construct 4-story single family & adu
- Filed
- Jul 1, 2021
- Issued
- Aug 12, 2026 (61 months after filing)
- Completed
- Not completed yet
- Review stops
- 29 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 2, 2021 | Jul 2, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2021 | Apr 27, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Apr 14, 2022 | Apr 18, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2023 | Feb 15, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 15, 2023 | Jul 30, 2026 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 28, 2023 | Apr 28, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 28, 2023 | Feb 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 28, 2023 | Jun 9, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2023 | Jun 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2023 | Mar 17, 2026 | — |
Urban forestry Public Works · DPW-BUF | May 3, 2023 | Apr 5, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Feb 27, 2026 | Mar 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 4, 2026 | Mar 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2026 | Mar 11, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 31, 2026 | Mar 31, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2026 | Apr 2, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2026 | Apr 8, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Apr 21, 2026 | May 21, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 22, 2026 | May 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 26, 2026 | May 26, 2026 | Approved |
Address verification Building Inspection · ADDR | May 28, 2026 | Jun 5, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 28, 2026 | May 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | May 28, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 28, 2026 | Jun 5, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Jun 15, 2026 | Jul 30, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2026 | Aug 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,987,883
| Name | Role | License on permit |
|---|---|---|
| Strachan G Forgan | Architect | C-38182 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2017