1504 Jerrold Av
San Francisco permit 202107023732 · Bayview Hunters Point
Renovate 2-story home. add (n)3/f w/ (n)kit & bathrm. exterior finish replacement, re-grading (e)sidewalk at entry, rebuild (e)low rear yard. retaining wall, (n)rear yard flat-work, install solar roof system. structural work -full seismic upgrade for vert addition. mep.
- Filed
- Jul 2, 2021
- Issued
- Dec 12, 2022 (17 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 4 departments
- Comments issued
- None
- Put on hold
- 8 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 18, 2021 | Aug 18, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 18, 2021 | Jul 19, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Apr 26, 2022 | Apr 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2022 | Jul 7, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2022 | Sep 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2022 | Nov 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2022 | Oct 12, 2022 | — |
Urban forestry Public Works · DPW-BUF | Nov 3, 2022 | Nov 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 22, 2022 | Nov 30, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 30, 2022 | Dec 12, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2022 | Dec 21, 2022 | — |
Addendum 1: Foundation, struc, arch, mep, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 17, 2023 | Feb 17, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 17, 2023 | May 25, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2023 | May 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 17, 2023 | Oct 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 17, 2023 | Feb 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 17, 2023 | Oct 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | May 25, 2023 | May 30, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 25, 2023 | Jun 8, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 8, 2023 | Jun 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2023 | Oct 5, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 11, 2023 | Oct 11, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Oct 11, 2023 | Oct 16, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2023 | Oct 13, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2023 | Oct 16, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2023 | Apr 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $630,596
| Name | Role | License on permit |
|---|---|---|
| Susan G Aitken Hamilton & Aitken Arch. | Architect | C17466 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025