3738 20th St #0
San Francisco permit 202107083934 · Mission
(n) decks off rear wall at 1st, 2nd & 3rd flrs. rebuild (e) exit stair from 3rd flr to rear yard. (n) site work for lower lvl infill, modifications & (n) finishes for (n) decks, (n) trash enclosure at front of house. 63 sq ft of (n) unconditioned infill on lower lvl under (e) 2nd flr.
- Filed
- Jul 8, 2021
- Issued
- Nov 13, 2023 (28 months after filing)
- Completed
- Mar 5, 2026 (28 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 22, 2021 | Jul 22, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 22, 2021 | Jun 12, 2023 | — |
Planning neighborhood notice Planning · CP-NP | May 25, 2022 | Jun 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2023 | Mar 10, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2023 | Oct 30, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jun 13, 2023 | Sep 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2023 | Jul 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 13, 2023 | Sep 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2023 | Jul 19, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2023 | Sep 25, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2023 | Sep 26, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 21, 2023 | Oct 25, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 21, 2023 | Sep 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2023 | Oct 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 6, 2023 | Oct 16, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 6, 2023 | Oct 10, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2023 | Oct 12, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 25, 2023 | Oct 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 25, 2023 | Oct 25, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2023 | Oct 25, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2023 | Oct 27, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2023 | Nov 13, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Kevin Hugo Zeller | Architect | C32204 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024