1500 Sunnydale Av
San Francisco permit 202107124132 · Visitacion Valley
Priority processing. mayor's dir #17-02. erect a 2-story, type 3b,community center with childcare center. 1500 sunnydale aka 1550 sunnydale
- Filed
- Jul 12, 2021
- Issued
- Apr 6, 2022 (9 months after filing)
- Completed
- Oct 15, 2024 (30 months after issuance)
- Review stops
- 70 stops across 6 departments
- Comments issued
- 6 times, by Fire Department, Building Inspection
- Put on hold
- 16 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 12, 2021 | Aug 2, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 2, 2021 | Mar 24, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 3, 2021 | Mar 21, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Oct 12, 2021 | Mar 16, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 12, 2021 | Feb 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 12, 2021 | Feb 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 12, 2021 | Feb 11, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 12, 2021 | Nov 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2022 | Mar 22, 2022 | — |
Development fee collection Building Inspection · DFCU | Mar 23, 2022 | Mar 24, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2022 | Apr 6, 2022 | — |
Addendum 1: Civil engineering, site shoring and underground utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 8, 2022 | Apr 11, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 11, 2022 | Jun 14, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 11, 2022 | Jun 15, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Apr 11, 2022 | Jun 2, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 11, 2022 | Jun 16, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2022 | Jun 23, 2022 | — |
Addendum 2: Foundation and superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 17, 2022 | Nov 4, 2022 | — |
Building plan review Building Inspection · BLDG | May 17, 2022 | Dec 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2022 | Jun 15, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | May 17, 2022 | Jun 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 17, 2022 | Dec 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 4, 2022 | Dec 21, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Nov 4, 2022 | Nov 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 28, 2022 | Dec 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2022 | Jan 5, 2023 | — |
Addendum 3: Fire protection, design build submitted by the subcontractor
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 8, 2022 | Aug 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 8, 2022 | Sep 13, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 8, 2022 | Sep 13, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2022 | Nov 4, 2022 | — |
Addendum 4: Architecture, landscape, mechanical, plumbing and electrical systems
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 1, 2022 | Nov 1, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 1, 2022 | Mar 16, 2023 | — |
Disability access review Mayor's Office on Disability · MOD | Nov 2, 2022 | Feb 9, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2022 | Feb 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 2, 2022 | Jan 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 2, 2022 | Feb 9, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 2, 2022 | Mar 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2022 | Nov 4, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 2, 2022 | Nov 17, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Nov 7, 2022 | Mar 10, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 20, 2023 | Mar 15, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 8, 2023 | Feb 9, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 8, 2023 | Feb 21, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2023 | Mar 14, 2023 | — |
Disability access review Mayor's Office on Disability · MOD | Mar 16, 2023 | Mar 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2023 | Mar 20, 2023 | — |
Addendum 5: Fire alarm, design build submitted by the subcontractor
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 8, 2023 | In progress | Administrative |
Fire prevention review Fire Department · SFFD | Nov 8, 2023 | Dec 13, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 8, 2023 | May 14, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 2, 2024 | Feb 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 10, 2024 | May 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 14, 2024 | Jun 3, 2024 | Administrative |
Addendum 6: Elevator, design build submitted by contractor (withdrawn)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 11, 2024 | Oct 11, 2024 | Administrative |
Addendum 7: Photovoltaic system, design build submitted by contractor
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 20, 2023 | Jul 20, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2023 | Aug 1, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2023 | Jul 26, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 20, 2023 | Aug 1, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 20, 2023 | Jan 9, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jul 24, 2023 | Jul 26, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 22, 2023 | Sep 7, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 22, 2023 | Aug 25, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 22, 2023 | Aug 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2023 | Oct 3, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 11, 2023 | Dec 12, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 11, 2023 | Dec 12, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 11, 2023 | Dec 11, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 21, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 21, 2023 | Dec 21, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 21, 2023 | Jan 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2024 | Feb 2, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $17,700,000
| Name | Role | License on permit |
|---|---|---|
| Marsha Ann Maytum Leddy Maytum Stacy | Architect | C12450 |
| Greg R Wagner Kpff | Engineer | 4931 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025