475 28th St
San Francisco permit 202107154487 · Noe Valley
Basement addition, addition at kitchen/deck, add bay at rear facade at 2nd level, add 2 powder rooms, remodel 2 bathrooms and kitchen. new ground floor area is 1,198 sq. ft.
- Filed
- Jul 15, 2021
- Issued
- Dec 19, 2022 (17 months after filing)
- Completed
- Not completed yet
- Review stops
- 21 stops across 4 departments
- Comments issued
- None
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 1, 2021 | Sep 1, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 1, 2021 | Apr 26, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Feb 11, 2022 | Mar 8, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 27, 2022 | Dec 2, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2022 | Sep 1, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2022 | Sep 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2022 | Sep 9, 2022 | — |
Urban forestry Public Works · DPW-BUF | Oct 17, 2022 | Dec 1, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 5, 2022 | Dec 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 14, 2022 | Dec 19, 2022 | — |
Development fee collection Building Inspection · DFCU | Dec 15, 2022 | Dec 15, 2022 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Dec 20, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2022 | Jul 5, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2023 | Mar 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2023 | Sep 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2023 | Mar 21, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2023 | Sep 14, 2023 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2023 | Sep 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2023 | Sep 22, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 22, 2023 | Oct 11, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 11, 2023 | Jan 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $420,000
| Name | Role | License on permit |
|---|---|---|
| Beverly Ann Choe Bach Architecture | Architect | C29098 |
| Denny Chi-Ho Kwan Holmes Culley | Engineer | S4887 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022