CheckMyDesigner

300 De Haro St

San Francisco permit 202107235031 · Mission Bay

New buildingFull plan reviewIssued
Street view · Dec 2024
Google Street View of 300 De Haro St, Dec 2024
Scope of work
As written on the permit application.

100% affordable housing mayor ed 13-01: erect a new 11 story, mixed use public housing facility with 425 sleeping units and common use facilities, and two commercial restaurant tenant spaces at ground floor

Timeline
Key dates from the city record.
Filed
Jul 23, 2021
Issued
Mar 28, 2025 (44 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
156 stops across 8 departments
Comments issued
34 times, by Fire Department, Public Works, Public Health, Building Inspection, Permit Center
Put on hold
7 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 19, 2021—

Zoning review

Planning · CP-ZOC

Dec 15, 2021—

Permit Processing Center

Building Inspection · PPC

Mar 19, 2025Administrative

Building plan review

Building Inspection · BLDG

Nov 3, 2022—

Fire prevention review

Fire Department · SFFD

Feb 26, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 26, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 12, 2022—

CON

CON-BOND

Dec 16, 2022Approved

Zoning review

Planning · CP-ZOC

Oct 12, 2023Administrative

Public Health

HEALTH-MH

Mar 28, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Mar 10, 2023—

Building plan review

Building Inspection · BLDG

Mar 13, 2023—

Building plan review

Building Inspection · BLDG

Dec 9, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 27, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 11, 2025Issued Comments

Public Health

HEALTH-MH

Feb 11, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 19, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 14, 2025Approved

Fire prevention review

Fire Department · SFFD

Feb 25, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Feb 26, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 6, 2025Approved-Stipulated

Development fee collection

Building Inspection · DFCU

Mar 6, 2025Administrative

Public Health

HEALTH-MH

Mar 7, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 17, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 28, 2025Administrative

Addendum 1: Health

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 1, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 1, 2025Administrative

Public health review

Public Health · HEALTH

May 1, 2025Approved

Permit Processing Center

Building Inspection · PPC

May 2, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Jun 24, 2025Administrative

Addendum 2: Foundation, health

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 16, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 16, 2025Administrative

Building plan review

Building Inspection · BLDG

May 25, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 1, 2025Approved

Public health review

Public Health · HEALTH

Apr 17, 2025Administrative

Public Health

HEALTH-MH

Apr 21, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Jun 23, 2025Administrative

Public Health

HEALTH-HM

Apr 21, 2025Approved

Public Health

HEALTH-MH

Apr 24, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 17, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jun 23, 2025Approved

Public Health

HEALTH-MH

Jun 18, 2025Approved

Public Health

HEALTH-HM

Jun 20, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 26, 2025Administrative

Addendum 3: Superstructure

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 20, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 21, 2025Administrative

Building plan review

Building Inspection · BLDG

Sep 3, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 26, 2025Not Applicable

Street use and mapping

Public Works · DPW-BSM

May 30, 2025Approved

Permit Processing Center

Building Inspection · PPC

Oct 30, 2025Administrative

Building plan review

Building Inspection · BLDG

Oct 27, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 30, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 4, 2025Administrative

Addendum 4: Architecture, mep

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 8, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 22, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Nov 24, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 24, 2025Administrative

Zoning review

Planning · CP-ZOC

Feb 24, 2026Approved

Building plan review

Building Inspection · BLDG

Jan 22, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 11, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

Dec 11, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Dec 8, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 25, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 26, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Dec 12, 2025Approved

Plumbing plan check

Building Inspection · PID-PC

Dec 3, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Aug 5, 2026Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Dec 10, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Jan 22, 2026Administrative

Building plan review

Building Inspection · BLDG

Mar 17, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 12, 2026Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Mar 13, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Mar 19, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Mar 19, 2026Issued Comments

Plumbing plan check

Building Inspection · PID-PC

Apr 10, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Apr 17, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 29, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Apr 15, 2026Approved-Stipulated

Mechanical and energy plan review

Building Inspection · MECH

Apr 21, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Apr 29, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 5, 2026Approved

Zoning review

Planning · CP-ZOC

Aug 5, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jul 7, 2026Issued Comments

Public Utilities programs review

Public Utilities · SFPUC-PRG

Jul 8, 2026Approved

Plumbing plan check

Building Inspection · PID-PC

Jul 24, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 6, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Aug 3, 2026Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Addendum 5: Tower crane

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 16, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 17, 2025Administrative

Zoning review

Planning · CP-ZOC

Dec 15, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 14, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 14, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 22, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 23, 2025Not Applicable

Public Utilities programs review

Public Utilities · SFPUC-PRG

Oct 29, 2025Not Applicable

Plumbing plan check

Building Inspection · PID-PC

Oct 22, 2025Not Applicable

Permit Processing Center

Building Inspection · PPC

Jan 9, 2026Administrative

Building plan review

Building Inspection · BLDG

Dec 15, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 15, 2025Not Applicable

Building plan review quality control

Building Inspection · BLDG-QC

Dec 17, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 6, 2026Approved

Building plan review

Building Inspection · BLDG

Jan 6, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Jan 6, 2026Administrative

Street use and mapping

Public Works · DPW-BSM

Jan 8, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 6, 2026Not Applicable

Public Utilities programs review

Public Utilities · SFPUC-PRG

Jan 9, 2026Not Applicable

Central Permit Bureau

Building Inspection · CPB

Jan 15, 2026Administrative

Addendum 6: Metal stairs

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 14, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 14, 2026Administrative

Building plan review

Building Inspection · BLDG

Jun 15, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 15, 2026Not Applicable

Fire Department housing review

Fire Department · SFFD-HQ

Jun 8, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 30, 2026Administrative

Building plan review

Building Inspection · BLDG

Jul 30, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Jul 30, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 5, 2026Administrative

Addendum 7: Fire sprinklers

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 17, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 20, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Apr 29, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Oct 23, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Jun 30, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Jul 30, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Sep 10, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Oct 22, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 28, 2026Administrative

Addendum 9: Generator, fuel oil piping

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

In progressIn Progress

Central Permit Bureau

Building Inspection · CPB

In progress—

Addendum 12: Ground improvement.

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 28, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 28, 2025Administrative

Building plan review

Building Inspection · BLDG

Jun 2, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 3, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

Jun 5, 2025Approved

Public Health

HEALTH-MH

May 29, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jul 11, 2025Administrative

Building plan review

Building Inspection · BLDG

Jun 24, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jul 3, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 9, 2025Approved

Public Health

HEALTH-MH

Jul 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2025Administrative

Addendum 13: Rev 1 to addendum 4

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 3, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Nov 4, 2026Administrative

Address verification

Building Inspection · ADDR

In progress—

Zoning review

Planning · CP-ZOC

In progress—

Building plan review

Building Inspection · BLDG

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Electrical plan review

Building Inspection · MECH-E

In progress—

Fire Department housing review

Fire Department · SFFD-HQ

In progress—

Street use and mapping

Public Works · DPW-BSM

In progress—

Urban forestry

Public Works · DPW-BUF

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

In progress—

Public Utilities programs review

Public Utilities · SFPUC-PRG

In progress—

Plumbing plan check

Building Inspection · PID-PC

In progress—

Public Health

HEALTH-MH

In progress—

Permit Processing Center

Building Inspection · PPC

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Issued
Estimated cost
$75,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
William Philip Duncanson

Bar Architects

ArchitectC36407
Diarmuid Hugo Mac Neill

Dolmen Structural Engineer

EngineerC56739
Erwin J O'toole

Shorecal Engineering Inc

EngineerC-80734
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202107235031 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record