2130 Oakdale Av
San Francisco permit 202107295399 · Bayview Hunters Point
To propose 2674sf growing room w/ interior partition wall in the main floor. adding 1426sf mezzanine for 1301sf growing room and storage in (e) mezzanine w/ associated mep work in (e) horticultural warehouse.
- Filed
- Jul 29, 2021
- Issued
- Mar 20, 2023 (20 months after filing)
- Completed
- Dec 9, 2024 (21 months after issuance)
- Review stops
- 19 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 29, 2021 | Jul 29, 2021 | — |
Electrical inspector Building Inspection · EID-INSP | Aug 20, 2021 | Aug 20, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Aug 20, 2021 | Aug 20, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 20, 2021 | Aug 23, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2021 | Aug 23, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 25, 2021 | Oct 6, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 7, 2021 | Aug 29, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 7, 2021 | Nov 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2022 | Sep 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 14, 2022 | Dec 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2022 | May 19, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 3, 2022 | Aug 29, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 3, 2022 | Jan 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2022 | Oct 5, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 21, 2022 | Dec 29, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 18, 2023 | Jan 27, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 31, 2023 | Feb 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2023 | Feb 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2023 | Mar 20, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $393,850
| Name | Role | License on permit |
|---|---|---|
| Hau-Ching Liao Ladc Consulting Inc | Architect | C28947 |
| Yu Yan Zenith Engineers Inc | Engineer | C90749 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026