2475 Harrison St
San Francisco permit 202108025591 · Mission
Horizontal addition at 3rd flr. (n) rated window at prop-line at north side on 2nd flr. 2 (n) bedrms, (n) bath & (n) laundry at 3rd flr. enlarged fam rom, kitchen & dining rm, (n) powder rm & storage rm
- Filed
- Aug 2, 2021
- Issued
- Apr 19, 2022 (9 months after filing)
- Completed
- Apr 23, 2024 (24 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 16, 2021 | Aug 16, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 16, 2021 | Jan 11, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Nov 10, 2021 | Nov 16, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 14, 2022 | Feb 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2022 | Feb 25, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 1, 2022 | Mar 21, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 23, 2022 | Apr 6, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Mar 23, 2022 | Apr 6, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 8, 2022 | Apr 8, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2022 | Apr 19, 2022 | — |
Addendum 1: Final: foundation, architectural, superstructure, t24, mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 26, 2022 | Apr 26, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2022 | Jun 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2022 | Jul 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2022 | Aug 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2022 | Jun 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 10, 2022 | Aug 10, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2022 | Aug 29, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Killian O'sullivan O'sullivan Architecture | Architect | C-30355 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025