CheckMyDesigner

127 26th Av

San Francisco permit 202108045827 · Seacliff

AdditionFull plan reviewComplete
Street view · May 2019
Google Street View of 127 26th Av, May 2019
Scope of work
As written on the permit application.

Horizontal expansion >10' at rear, ar ground, 1st, + 2nd floors. vertical expansion >7' at rear, to create partial 3rd floor + roof deck w/ height variance for max 33" abv height envelope. renovate (e) 1st + 2nd floors, adding (1) full bath. (n) rearyard deck + stair. excavation at ground flr

Timeline
Key dates from the city record.
Filed
Aug 4, 2021
Issued
Mar 1, 2023 (19 months after filing)
Completed
Feb 26, 2026 (36 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
7 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 17, 2021—

Zoning review

Planning · CP-ZOC

Aug 12, 2022—

Planning neighborhood notice

Planning · CP-NP

Jun 14, 2022—

Building plan review

Building Inspection · BLDG

Dec 1, 2022—

Street use and mapping

Public Works · DPW-BSM

Feb 1, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Nov 15, 2022—

Building plan review

Building Inspection · BLDG

Dec 22, 2022—

Building plan review

Building Inspection · BLDG

Jan 17, 2023—

Building plan review

Building Inspection · BLDG

Jan 30, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 2, 2023—

Zoning review

Planning · CP-ZOC

Feb 21, 2023—

Permit Processing Center

Building Inspection · PPC

Feb 22, 2023—

Central Permit Bureau

Building Inspection · CPB

Mar 1, 2023—

Addendum 1: Structural/arch/mep final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 20, 2023—

Building plan review

Building Inspection · BLDG

May 5, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 22, 2023—

Street use and mapping

Public Works · DPW-BSM

May 30, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 24, 2023—

Permit Processing Center

Building Inspection · PPC

May 30, 2023—

Building plan review

Building Inspection · BLDG

May 24, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 22, 2023—

Central Permit Bureau

Building Inspection · CPB

May 31, 2023—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$479,256
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Stephen G Verner

Verner Architects

ArchitectC34368
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202108045827 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record