2201 Powell St
San Francisco permit 202108055863 · North Beach
At&t: 4 panel antennas within (4) frp vents. 10 rru's, 2 dc9 surge suppressors, 1 gps, hybrid cable route to equipment. install 1 vertiv dcpp, 1 purcell in basement, 3 vertiv bat. enclouser w/ 3 strings 190ah batteries, 1 h-frame, 200aac power panel on h-frame, 1 ciena and hoffman box on h-frame.
- Filed
- Aug 5, 2021
- Issued
- Jun 28, 2022 (11 months after filing)
- Completed
- May 13, 2024 (23 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 5, 2021 | Aug 5, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 5, 2021 | Aug 5, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 5, 2021 | Aug 5, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2021 | Aug 5, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 5, 2021 | Aug 26, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Aug 26, 2021 | Aug 26, 2021 | — |
Public health review Public Health · HEALTH | Aug 26, 2021 | Aug 26, 2021 | — |
Intake Building Inspection · INTAKE | Jan 27, 2022 | Jan 27, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2022 | Jan 27, 2022 | — |
Intake Building Inspection · INTAKE | Apr 29, 2022 | Apr 29, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 29, 2022 | Apr 29, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 29, 2022 | Apr 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2022 | Apr 29, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2022 | Apr 29, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 29, 2022 | Apr 29, 2022 | — |
Public health review Public Health · HEALTH | Apr 29, 2022 | Apr 29, 2022 | — |
Electrical plan review Building Inspection · MECH-E | May 10, 2022 | May 10, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 28, 2022 | Jun 28, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Wissam Zalzali All States Engineering | Engineer | C71655 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025