1180 Evans Av
San Francisco permit 202108065970 · Bayview Hunters Point
Erect a new 3 stories with no basement electrical switchgear/storage. type 2-a
- Filed
- Aug 6, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 20 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 10 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 6, 2021 | Aug 24, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 24, 2021 | Sep 23, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 24, 2021 | Sep 12, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2021 | Mar 21, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2021 | Jun 29, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 23, 2021 | Jul 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 23, 2021 | Mar 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2021 | Nov 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2021 | Jul 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2022 | Jan 24, 2022 | — |
Urban forestry Public Works · DPW-BUF | Feb 8, 2022 | Jul 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 5, 2022 | Jul 5, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 26, 2022 | Jul 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 26, 2022 | Jul 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2022 | Jul 28, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jul 26, 2022 | Jul 27, 2022 | — |
Development fee collection Building Inspection · DFCU | Jul 29, 2022 | Aug 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2022 | In progress | — |
Public health review Public Health · HEALTH | Aug 16, 2022 | Aug 29, 2022 | — |
Public Health HEALTH-MH | Aug 16, 2022 | Aug 16, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Approved
- Estimated cost
- $16,000,000
| Name | Role | License on permit |
|---|---|---|
| Paul I Cooper Tef Design | Architect | C28490 |
| Joseph Kenneth Young Bkf | Engineer | C84619 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026