272 Eureka St
San Francisco permit 202108106180 · Castro/Upper Market
Addition at 1st & 2nd flrs. extend by appx 9'-7 1/2". adding 224 sq ft to each level. relocate pwdr rm, replace (e) wood deck, (n) sliding door & window at rear, add (n) bath rm-laundry-office & skylight. renovate kitchen.
- Filed
- Aug 10, 2021
- Issued
- Nov 1, 2022 (15 months after filing)
- Completed
- Apr 16, 2025 (29 months after issuance)
- Review stops
- 27 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 12, 2021 | Aug 12, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 12, 2021 | May 20, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Mar 18, 2022 | Mar 23, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | May 18, 2022 | May 18, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 6, 2022 | Jul 5, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 5, 2022 | Aug 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 15, 2022 | Sep 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2022 | Oct 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 12, 2022 | Sep 19, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 11, 2022 | Oct 12, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 14, 2022 | Oct 18, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 19, 2022 | Oct 27, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 20, 2022 | Oct 25, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 27, 2022 | Nov 1, 2022 | — |
Addendum 1: Struct,archt,t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 4, 2022 | Nov 4, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2022 | Mar 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2023 | Mar 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 6, 2023 | Mar 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2023 | Mar 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2023 | Mar 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2023 | Mar 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2023 | Mar 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2023 | Mar 28, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2023 | Mar 29, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 29, 2023 | Mar 31, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2023 | Mar 31, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2023 | Apr 3, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $373,273
| Name | Role | License on permit |
|---|---|---|
| Jack Thomas Backus Jack Backus Architects | Architect | c30743 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025