Scope of work
As written on the permit application.

Convert existing first floor storage/ basement of four story multi-family residential building to one adu.

Timeline
Key dates from the city record.
Filed
Aug 20, 2021
Issued
Oct 11, 2024 (38 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
3 times, by Building Inspection
Put on hold
10 times
Review stopFinishedResult

Planning review

Planning · CP-GEN

Sep 1, 2021—

Building inspector

Building Inspection · BID-INSP

Sep 3, 2021—

Zoning review

Planning · CP-ZOC

Jul 6, 2023—

Building plan review

Building Inspection · BLDG

Dec 7, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 14, 2023—

Fire prevention review

Fire Department · SFFD

Sep 13, 2021—

Street use and mapping

Public Works · DPW-BSM

Mar 21, 2022—

Urban forestry

Public Works · DPW-BUF

Dec 26, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 23, 2021—

Planning discretionary review

Planning · CP-DR

Jul 6, 2023—

Fire prevention review

Fire Department · SFFD

Mar 6, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Feb 16, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 16, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 4, 2024In Progress

Planning review

Planning · CP-GEN

Feb 15, 2023—

Public Health

HEALTH-MH

Apr 5, 2023—

Zoning review

Planning · CP-ZOC

Jan 30, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 28, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Jan 2, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Dec 21, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Dec 28, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 29, 2023Approved

Public Health

HEALTH-MH

Dec 21, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 28, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 1, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 5, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 5, 2024Approved

Public Health

HEALTH-MH

Mar 18, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 21, 2024Approved

Urban forestry

Public Works · DPW-BUF

Mar 29, 2024Approved

Development fee collection

Building Inspection · DFCU

Mar 29, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Oct 11, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$460,922
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ethan C Andersen

Drafting Cafe Architects

Architect34235
Calin Smith

Smith Engineering, Inc.

EngineerC-57642
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202108206824 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record