372 Dolores St #0
San Francisco permit 202108206824 · Castro/Upper Market
Convert existing first floor storage/ basement of four story multi-family residential building to one adu.
- Filed
- Aug 20, 2021
- Issued
- Oct 11, 2024 (38 months after filing)
- Completed
- Not completed yet
- Review stops
- 32 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 10 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Aug 20, 2021 | Sep 1, 2021 | — |
Building inspector Building Inspection · BID-INSP | Sep 1, 2021 | Sep 3, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 1, 2021 | Jul 6, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 1, 2021 | Dec 7, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2021 | Feb 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 1, 2021 | Sep 13, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2021 | Mar 21, 2022 | — |
Urban forestry Public Works · DPW-BUF | Sep 1, 2021 | Dec 26, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2021 | Sep 23, 2021 | — |
Planning discretionary review Planning · CP-DR | Oct 21, 2022 | Jul 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 14, 2023 | Mar 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 14, 2023 | Feb 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2023 | Feb 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 14, 2023 | Apr 4, 2024 | In Progress |
Planning review Planning · CP-GEN | Feb 15, 2023 | Feb 15, 2023 | — |
Public Health HEALTH-MH | Apr 4, 2023 | Apr 5, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2023 | Jan 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 28, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 21, 2023 | Jan 2, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 21, 2023 | Dec 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 21, 2023 | Dec 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 21, 2023 | Dec 29, 2023 | Approved |
Public Health HEALTH-MH | Dec 21, 2023 | Dec 21, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 6, 2024 | Feb 28, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 1, 2024 | Mar 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 4, 2024 | Mar 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2024 | Mar 5, 2024 | Approved |
Public Health HEALTH-MH | Mar 15, 2024 | Mar 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2024 | Mar 21, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 15, 2024 | Mar 29, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Mar 29, 2024 | Mar 29, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 4, 2024 | Oct 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $460,922
| Name | Role | License on permit |
|---|---|---|
| Ethan C Andersen Drafting Cafe Architects | Architect | 34235 |
| Calin Smith Smith Engineering, Inc. | Engineer | C-57642 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025