489 Corbett Av
San Francisco permit 202108307422 · Castro/Upper Market
Vertical & horizontal addition. 505 sq ft 4th flr addition to an (e) two family dwellingwork includes 147.4 sq ft addition to (e) third floor, new windows and doors, (n) decks, (n) staircase from the (e) third floor to the (n) fourth level.
- Filed
- Aug 30, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 17 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 29, 2021 | Sep 29, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 29, 2021 | Dec 20, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2022 | Aug 1, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Oct 24, 2022 | Oct 24, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Dec 21, 2022 | Mar 6, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2023 | Feb 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 14, 2023 | Aug 30, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 30, 2023 | Sep 22, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2023 | Sep 25, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 31, 2023 | Mar 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Apr 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Mark David English Mark English Architects | Architect | C18594 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025