162 Alpine Tr
San Francisco permit 202109027657 · Castro/Upper Market
Interior remodel including kitchen and (e) bathroom. replace all windows. adding 3/4 bathroom o lower level & 1/2 bath on entrey level, reroof non-visible. visible window replacement under seperate permit.
- Filed
- Sep 2, 2021
- Issued
- Dec 14, 2022 (15 months after filing)
- Completed
- Dec 26, 2025 (36 months after issuance)
- Review stops
- 11 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 2, 2021 | Sep 2, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 2, 2021 | Sep 2, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 2, 2021 | Sep 2, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2021 | Sep 2, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Nov 18, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 18, 2021 | Nov 18, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2021 | Nov 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2021 | Dec 9, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 10, 2021 | Oct 26, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 28, 2022 | Oct 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2022 | Dec 14, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| Richard Ruff Ruff + Associates | Architect | C11736 |
| Nilgun Asci Wolpe Ny Engineering Consulting | Engineer | 68482 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025