314 Twin Peaks Bl
San Francisco permit 202109027666 · Twin Peaks
Addition at (e) roof deck attached to (e) stair enclosure. plus replacing & extending (e) balcony at 1st flr & back yard modification to (e) exterior deck on grade w/ outdoor wet bar & pool / hot tub combination.
- Filed
- Sep 2, 2021
- Issued
- May 24, 2023 (21 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 4 departments
- Comments issued
- Once, by Public Works
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 23, 2021 | Sep 23, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 23, 2021 | Nov 9, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Feb 11, 2022 | Feb 22, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 10, 2022 | Feb 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 18, 2023 | Mar 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2023 | Mar 3, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 24, 2023 | Feb 24, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 6, 2023 | Mar 9, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 13, 2023 | Mar 15, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 15, 2023 | May 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 3, 2023 | May 24, 2023 | — |
Addendum 1: Architectural, t-24, structural, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 25, 2023 | May 25, 2023 | — |
Building plan review Building Inspection · BLDG | May 25, 2023 | Nov 30, 2023 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 29, 2023 | Jun 29, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Jul 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2023 | Jul 27, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2023 | Jul 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 9, 2024 | Jul 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Jul 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Jul 30, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 30, 2024 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $221,007
| Name | Role | License on permit |
|---|---|---|
| Albert J Costa Costa Brown Architecture | Architect | C25678 |
| Matthew Bryan Tropp Ashley & Vance | Engineer | S5683 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026