5624 Anza St
San Francisco permit 202109077890 · Outer Richmond
Construct new 648sqft accessory dwelling unit within first floor unfinished space, excavate about 44 cubic yards and install new slab, install new laundry closet with new hook up, install new on demand hot water heater, install ducted mini heat pump system, work in upper unit removing a window and..
- Filed
- Sep 7, 2021
- Issued
- Aug 19, 2024 (35 months after filing)
- Completed
- Not completed yet
- Review stops
- 42 stops across 4 departments
- Comments issued
- None
- Put on hold
- 11 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Sep 7, 2021 | Sep 7, 2021 | — |
Building inspector Building Inspection · BID-INSP | Sep 7, 2021 | Sep 9, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 7, 2021 | Sep 2, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 7, 2021 | May 2, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 7, 2021 | Apr 29, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2021 | Sep 13, 2021 | — |
Urban forestry Public Works · DPW-BUF | Sep 7, 2021 | May 8, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 7, 2021 | Sep 28, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2022 | Mar 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2022 | Mar 16, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 11, 2022 | May 2, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2022 | May 19, 2022 | — |
Building plan review Building Inspection · BLDG | May 2, 2022 | Jun 27, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | May 2, 2022 | Jun 27, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2022 | Jun 8, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2022 | Aug 26, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2022 | Jun 2, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 1, 2022 | Jun 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2022 | Aug 29, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 25, 2022 | Aug 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2022 | Aug 26, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 2, 2022 | Sep 22, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 16, 2022 | May 5, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 16, 2022 | Mar 29, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 16, 2022 | Mar 29, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 16, 2022 | Dec 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 16, 2022 | Dec 1, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 16, 2022 | Nov 17, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2023 | Apr 28, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 29, 2023 | Apr 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2023 | Apr 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2023 | Apr 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 13, 2023 | Apr 13, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 20, 2023 | Jun 20, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 20, 2023 | Jun 22, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 20, 2023 | Jun 20, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 20, 2023 | Jun 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 20, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2023 | Jun 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2023 | Jun 30, 2023 | — |
Development fee collection Building Inspection · DFCU | Jun 30, 2023 | Jun 30, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 30, 2023 | Aug 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Thornton Weiler Thornton Weiler Architect | Architect | C27685 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2026