3821 Noriega St
San Francisco permit 202109158510 · Sunset/Parkside
Alteration of ground floor commercial building of type v construction with the addition of 3 stories of r-2 residential type v-a construction above. the proposed addition will provide 1 residential unit per floor with a private terrace at the second floor rear yard and a common area roof deck.
- Filed
- Sep 15, 2021
- Issued
- Jul 10, 2023 (22 months after filing)
- Completed
- Not completed yet
- Review stops
- 23 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 15, 2021 | Sep 15, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 29, 2021 | Jul 20, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 29, 2021 | Jun 5, 2023 | — |
Planning neighborhood notice Planning · CP-NP | May 10, 2022 | May 11, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 25, 2022 | Dec 20, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 25, 2022 | May 19, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2022 | Sep 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2022 | Aug 3, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2022 | Jan 31, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 31, 2023 | May 3, 2023 | — |
Building plan review Building Inspection · BLDG | May 3, 2023 | May 11, 2023 | — |
Fire prevention review Fire Department · SFFD | May 19, 2023 | May 19, 2023 | — |
Zoning review Planning · CP-ZOC | May 19, 2023 | May 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 19, 2023 | Jun 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2023 | May 24, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 1, 2023 | Jun 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2023 | Jul 10, 2023 | — |
Addendum 1: Foundation, superstructure,
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Nov 29, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Jan 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 29, 2023 | Nov 30, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Nov 29, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,250,982
| Name | Role | License on permit |
|---|---|---|
| David Nelson Sternberg Sternberg Benjamin Architects | Architect | C11102 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015