2020 Jennings St
San Francisco permit 202109208710 · Bayview Hunters Point
Alterations for code compliance at existing, non-permitted 1st floor dwelling unit. legalize ground floor unit per ordinance 43-14. add spiral staicase to 2nd floor unit.
- Filed
- Sep 20, 2021
- Issued
- Dec 4, 2025 (50 months after filing)
- Completed
- Not completed yet
- Review stops
- 27 stops across 4 departments
- Comments issued
- 12 times, by Building Inspection, Public Works
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 20, 2021 | Oct 4, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 4, 2021 | May 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 7, 2024 | Jun 17, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 7, 2024 | Jul 8, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | May 23, 2024 | May 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2024 | Aug 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2024 | Aug 6, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 6, 2024 | Aug 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 18, 2024 | Jan 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 30, 2025 | Jan 31, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 15, 2025 | Mar 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2025 | May 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2025 | May 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2025 | Jun 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 11, 2025 | Jun 23, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2025 | Jun 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2025 | Jul 1, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 2, 2025 | Jul 25, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2025 | Jul 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 28, 2025 | Aug 5, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 24, 2025 | Oct 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 27, 2025 | Oct 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2025 | Oct 31, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2025 | Oct 31, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 31, 2025 | Nov 5, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2025 | Dec 4, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $245,574
| Name | Role | License on permit |
|---|---|---|
| Michael Andreas Froehlich Mf Architect | Engineer | C24111 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026