1210 40th Av
San Francisco permit 202109218890 · Sunset/Parkside
Convert existing livable space into adu 500 sf, add new interior stairs, add new skylight in bathroom. add power and office to main on ground 1st fl. add new stairs between garage and main unit at 2nd fl.
- Filed
- Sep 21, 2021
- Issued
- Jul 25, 2023 (22 months after filing)
- Completed
- Feb 4, 2025 (18 months after issuance)
- Review stops
- 29 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 11 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Sep 21, 2021 | Sep 30, 2021 | — |
Building inspector Building Inspection · BID-INSP | Sep 30, 2021 | Oct 1, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 30, 2021 | Apr 26, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 30, 2021 | Apr 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 30, 2021 | Jan 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2021 | Dec 1, 2022 | — |
Urban forestry Public Works · DPW-BUF | Sep 30, 2021 | Jun 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2021 | Aug 1, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 5, 2021 | Jan 5, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 5, 2021 | Apr 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Aug 1, 2022 | Jun 28, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 29, 2022 | Nov 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2023 | Jan 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 13, 2023 | May 22, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2023 | May 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2023 | Apr 13, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2023 | May 30, 2023 | — |
Zoning review Planning · CP-ZOC | May 18, 2023 | May 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 18, 2023 | May 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 18, 2023 | May 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 31, 2023 | Jun 1, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 1, 2023 | Jun 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2023 | Jun 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2023 | Jun 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 1, 2023 | Jun 9, 2023 | — |
Development fee collection Building Inspection · DFCU | Jun 27, 2023 | Jun 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 28, 2023 | Jul 25, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| Lavern John Wulfekuhle | Architect | 37670 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022