375 Laguna Honda Bl
San Francisco permit 202109239018 · Twin Peaks
Replacement of water tank #2. including new security(fencing,lighting) & access road improvements.(1)new site lighting & security camera power under emergency life-safety branch power at the water tank area to enchanced hospital security & site egress sytem,(2)no fire supression scope is included
- Filed
- Sep 23, 2021
- Issued
- Feb 5, 2024 (28 months after filing)
- Completed
- Not completed yet
- Review stops
- 11 stops across 5 departments
- Comments issued
- None
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 23, 2021 | Oct 4, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 4, 2021 | Sep 8, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2021 | Dec 13, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2022 | Dec 5, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2022 | Nov 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 8, 2022 | Dec 2, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 8, 2022 | Sep 9, 2022 | — |
Public Works disability access review Public Works · PW-DAC | Sep 8, 2022 | Sep 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2022 | Sep 26, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 28, 2022 | Dec 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2022 | Feb 5, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,303,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey Jon Tarantino | Engineer | C63936 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022