4758 Mission St
San Francisco permit 202109289290 · Outer Mission
Proposed interior remodeling of (e) 3-story over basement building to accomodate (8) (n) residential units. all work to be performed within (e) boundary of the building.
- Filed
- Sep 28, 2021
- Issued
- Apr 8, 2024 (30 months after filing)
- Completed
- Not completed yet
- Review stops
- 41 stops across 6 departments
- Comments issued
- 12 times, by Planning, Building Inspection, Public Works
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Electrical inspector Building Inspection · EID-INSP | Sep 27, 2021 | Sep 27, 2021 | — |
Code enforcement Building Inspection · CES | Sep 27, 2021 | Sep 27, 2021 | — |
Apartment and hotel inspection Building Inspection · HIS | Sep 28, 2021 | Sep 28, 2021 | — |
Intake Building Inspection · INTAKE | Sep 28, 2021 | Sep 28, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 29, 2021 | Mar 22, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 28, 2022 | Mar 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 21, 2022 | Jun 21, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2022 | Aug 7, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 28, 2022 | Jul 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 8, 2022 | Feb 12, 2024 | — |
Street use and mapping Public Works · DPW-BSM | Dec 29, 2022 | Dec 30, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 3, 2023 | Feb 22, 2024 | — |
Zoning review Planning · CP-ZOC | Feb 10, 2023 | Feb 15, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 7, 2023 | Aug 24, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 18, 2023 | Sep 25, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 28, 2023 | Oct 12, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Dec 8, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Jan 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 29, 2024 | Feb 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2024 | Feb 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2024 | Feb 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2024 | Feb 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 6, 2024 | Mar 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2024 | Mar 15, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 18, 2024 | Mar 18, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2024 | Apr 8, 2024 | Administrative |
Addendum 1: Foundation & framing.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 16, 2024 | Apr 25, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 17, 2024 | Apr 17, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2024 | Apr 25, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 19, 2024 | Apr 19, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 19, 2024 | Apr 19, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 25, 2024 | May 21, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 25, 2024 | May 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 25, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jun 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 31, 2024 | Aug 7, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 26, 2024 | Aug 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $3,696,673
| Name | Role | License on permit |
|---|---|---|
| Siavash Tahbazof Sia Consulting Corporation | Architect | C38827 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025