1001 Minnesota St
San Francisco permit 202109299493 · Potrero Hill
Expansion of (e) restaurant into adj space. (n) bar & bar equip; (n) ada & non-ada unisex washrooms as req; (n) aux kitchen w/ type ii hood; (e) kitchen remodel w/ (n) type 1 hood; (n) non-load bearing walls; (n) finishes, fixtures & equip;(n) unfixed tables & chairs.
- Filed
- Sep 29, 2021
- Issued
- Mar 14, 2022 (5 months after filing)
- Completed
- Aug 12, 2022 (5 months after issuance)
- Review stops
- 17 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 29, 2021 | Sep 29, 2021 | — |
Intake Building Inspection · INTAKE | Sep 29, 2021 | Sep 29, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 30, 2021 | Oct 5, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 12, 2021 | Oct 12, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 12, 2021 | Oct 12, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Oct 12, 2021 | Oct 12, 2021 | — |
Fire prevention review Fire Department · SFFD | Oct 12, 2021 | Oct 12, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2021 | Oct 18, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 20, 2021 | Oct 20, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2022 | Jan 21, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 21, 2022 | Jan 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 24, 2022 | Jan 25, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 26, 2022 | Feb 4, 2022 | — |
Public health review Public Health · HEALTH | Feb 4, 2022 | Feb 23, 2022 | — |
Development fee collection Building Inspection · DFCU | Mar 4, 2022 | Mar 4, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2022 | Mar 11, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2022 | Mar 14, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Cameron Helland Helland Architecture | Architect | C35654 |
| Ca Hien Voong Ca Voong | Engineer | 56997 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022