56 Toledo Wy
San Francisco permit 202110019621 · Marina
New vertical addition & roof deck on the 4/f. a new rooftop deck is also propsed above the 4/f. interior remodel of (e) 3 floors with new conditioned spaced on the g/f. building shall be equipped througout the nfpa 13r sprinkler system.
- Filed
- Oct 1, 2021
- Issued
- Sep 7, 2023 (23 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 6 departments
- Comments issued
- 4 times, by Fire Department, Building Inspection, Public Works
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 1, 2021 | Oct 1, 2021 | Administrative |
Zoning review Planning · CP-ZOC | Oct 1, 2021 | Nov 15, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Sep 14, 2022 | Sep 19, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 9, 2022 | Nov 9, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 16, 2022 | Feb 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 4, 2023 | Aug 15, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2023 | Aug 16, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2023 | Feb 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 15, 2023 | Aug 15, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 17, 2023 | Aug 24, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2023 | Aug 30, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 31, 2023 | Aug 31, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2023 | Sep 7, 2023 | Administrative |
Addendum 1: Final - superstructure, framing, foundation, mech & t24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 3, 2024 | Mar 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2024 | Mar 19, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Mar 6, 2024 | Mar 6, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 6, 2024 | Mar 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | May 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2024 | Apr 26, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2024 | Mar 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Mar 22, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 19, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Jul 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 27, 2024 | Jul 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $954,000
| Name | Role | License on permit |
|---|---|---|
| Grant Takahashi Lee Grant Takahashi Lee Architects | Architect | C31769 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2024