600 20th St
San Francisco permit 202110019676 · Potrero Hill
To construct a 5-story, type 1b, mixed use building with office/lab use at levels 1-4 and a residential dwelling unit at level 5. **comply w/ maher ord# 155-13, route to dph**
- Filed
- Oct 1, 2021
- Issued
- Mar 7, 2025 (41 months after filing)
- Completed
- Not completed yet
- Review stops
- 51 stops across 6 departments
- Comments issued
- 16 times, by Building Inspection, Fire Department, Public Works, Public Utilities
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Zoning review Planning · CP-ZOC | May 30, 2018 | May 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2021 | Oct 5, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 5, 2021 | Mar 4, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Oct 5, 2021 | Jan 30, 2025 | Administrative |
Public Health HEALTH-HM | Mar 5, 2023 | Mar 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 5, 2024 | Mar 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 5, 2024 | Mar 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2024 | Mar 12, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2024 | Mar 8, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Mar 5, 2024 | Mar 8, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 7, 2024 | Mar 7, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 15, 2024 | Apr 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2024 | Mar 15, 2024 | Approved |
Public Health HEALTH-MH | Mar 15, 2024 | Apr 9, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 18, 2024 | May 7, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 3, 2024 | May 17, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2024 | Apr 12, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2024 | Apr 4, 2024 | Approved |
Public Health HEALTH-HM | Apr 4, 2024 | Apr 4, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 18, 2024 | Apr 18, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 7, 2024 | May 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 15, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 29, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 13, 2024 | May 23, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 13, 2024 | May 17, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 13, 2024 | May 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 17, 2024 | Approved |
Public Health HEALTH-MH | May 13, 2024 | May 14, 2024 | Approved |
Public Health HEALTH-HM | May 13, 2024 | May 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2024 | Jun 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 18, 2024 | Jun 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2024 | Jul 1, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 18, 2024 | Jul 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2024 | Aug 16, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jun 18, 2024 | Jun 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2024 | Jun 25, 2024 | Approved |
Public Health HEALTH-HM | Jun 18, 2024 | Jun 18, 2024 | Approved |
Public Health HEALTH-MH | Jun 18, 2024 | Jun 20, 2024 | Approved |
Public Health HEALTH-HM | Jun 18, 2024 | Jun 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 16, 2024 | Aug 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 19, 2024 | Aug 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2024 | Aug 21, 2024 | Issued Comments |
Development fee collection Building Inspection · DFCU | Sep 3, 2024 | Sep 3, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 12, 2024 | Sep 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 10, 2025 | Jan 22, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2025 | Jan 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2025 | Jan 29, 2025 | Approved |
Public Health HEALTH-HM | Jan 22, 2025 | Jan 28, 2025 | Approved |
Public Health HEALTH-MH | Jan 22, 2025 | Jan 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2025 | Mar 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $10,200,000
| Name | Role | License on permit |
|---|---|---|
| Michael Howard Pitler Workshop1 | Architect | C30445 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026