4034 20th St
San Francisco permit 202110019688 · Castro/Upper Market
Bldg b: construction of new 3-story over basement, type vb, single family dwelling (with adu to be under separate permit). demo permit under pa# 202104269349.
- Filed
- Oct 1, 2021
- Issued
- Mar 17, 2022 (5 months after filing)
- Completed
- May 2, 2024 (26 months after issuance)
- Review stops
- 17 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 1, 2021 | Oct 4, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 4, 2021 | Nov 8, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2021 | Feb 23, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2021 | Feb 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 1, 2021 | Jan 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 1, 2021 | Feb 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2021 | Dec 17, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 1, 2021 | Jan 26, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 20, 2022 | Jan 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 20, 2022 | Jan 25, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2022 | Jan 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 26, 2022 | Feb 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2022 | Jan 28, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 26, 2022 | Feb 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2022 | Feb 14, 2022 | — |
Development fee collection Building Inspection · DFCU | Feb 23, 2022 | Feb 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2022 | Mar 17, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $570,000
| Name | Role | License on permit |
|---|---|---|
| Michael Bernard Harris Michael Harris Architecture | Architect | C15349 |
| Gordon Leonard Polon | Engineer | C28564 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022