Per adu ord# 162-16:convert portion of e 2 story sfr to attached, integral accessory dwelling unit. proposed adu converts 590 sf within conditioned 1st floor of (e) residence from den/storage to attached adu. new adu 39.8% of (e) gross building area. mep work.
- Filed
- Oct 8, 2021
- Issued
- Oct 18, 2022 (12 months after filing)
- Completed
- Feb 27, 2024 (16 months after issuance)
- Review stops
- 12 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 8, 2021 | Oct 8, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2021 | Feb 10, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 15, 2021 | Jan 24, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2021 | Dec 23, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2021 | Sep 20, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 11, 2022 | Oct 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2022 | Mar 1, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 1, 2022 | Aug 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 25, 2022 | Jun 6, 2022 | — |
Development fee collection Building Inspection · DFCU | Oct 11, 2022 | Oct 11, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 11, 2022 | Oct 11, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 11, 2022 | Oct 18, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $147,500
| Name | Role | License on permit |
|---|---|---|
| Bryan J Hassemer Inft3 Architecture & Design | Architect | C37092 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2018