518 Funston Av
San Francisco permit 202110120289 · Inner Richmond
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Relocation of (e) 2nd unit entrance door; window replacement in-kind 2 front facade in (e) masonry opening. no addtional sf revision to pa 2019-0802-7805
- Filed
- Oct 12, 2021
- Issued
- Apr 15, 2022 (6 months after filing)
- Completed
- Dec 8, 2022 (8 months after issuance)
- Review stops
- 4 stops across 2 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 12, 2021 | Oct 12, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2021 | Oct 12, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 13, 2021 | Oct 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2022 | Apr 15, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Michael P Ford Peters Design-Build | Architect | 36260 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2016