31 A Coleridge St
San Francisco permit 202110190707 · Bernal Heights
Restoration of rear shed in response to nov 202182671/202182672: new front facade and sistering of existing framing. fnd work
- Filed
- Oct 19, 2021
- Issued
- Dec 27, 2024 (38 months after filing)
- Completed
- Oct 3, 2025 (9 months after issuance)
- Review stops
- 12 stops across 4 departments
- Comments issued
- Twice, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 19, 2021 | Oct 19, 2021 | — |
Zoning review Planning · CP-ZOC | Mar 8, 2023 | Apr 23, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 9, 2024 | Jul 9, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 12, 2024 | Jul 12, 2024 | — |
Intake Building Inspection · INTAKE | Aug 20, 2024 | Aug 20, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Dec 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2024 | Dec 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2024 | Dec 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 17, 2024 | Dec 17, 2024 | Approved |
Building inspector Building Inspection · BID-INSP | Dec 27, 2024 | Dec 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 27, 2024 | Dec 27, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $80,000
| Name | Role | License on permit |
|---|---|---|
| Michael Andreas Froehlich Michael Froehlich Architect | Architect | C24111 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026