4458 24th St
San Francisco permit 202110190722 · Noe Valley
Addition of rear bedroom and bath, kitchen remodel, reconfigure front elevation and entry way(remodel front facade)
- Filed
- Oct 19, 2021
- Issued
- Apr 6, 2023 (18 months after filing)
- Completed
- Not completed yet
- Review stops
- 27 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 19, 2021 | Oct 25, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 25, 2021 | Jul 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 25, 2021 | Mar 20, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jun 1, 2022 | Jun 7, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 25, 2022 | Mar 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2022 | Sep 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2022 | Aug 1, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2023 | Mar 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 2, 2023 | Mar 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2023 | Mar 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2023 | Apr 6, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 26, 2023 | May 4, 2023 | — |
Building plan review Building Inspection · BLDG | May 4, 2023 | Oct 17, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2023 | Jun 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2023 | May 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 4, 2023 | Dec 15, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 4, 2023 | Mar 13, 2024 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Nov 7, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Nov 22, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2024 | Jan 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2024 | Feb 5, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2024 | Jan 24, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 14, 2024 | Feb 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 14, 2024 | Feb 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 14, 2024 | Mar 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2024 | Feb 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2024 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $130,000
| Name | Role | License on permit |
|---|---|---|
| Bruno P Kanter Kanter Architects | Architect | C26422 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019