4139 A Anza St
San Francisco permit 202110190799 · Outer Richmond
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision of 2017 0922 9356: renovate (e) exit passage way to have 3' width, 1-hr rated finishes. reswing doors & add a bike closet. (n) furnace tankless water heaters & laundry locations
- Filed
- Oct 19, 2021
- Issued
- Nov 16, 2021 (within 1 month of filing)
- Completed
- Sep 21, 2023 (22 months after issuance)
- Review stops
- 9 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Oct 19, 2021 | Oct 19, 2021 | — |
Intake Building Inspection · INTAKE | Oct 19, 2021 | Oct 19, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 20, 2021 | Oct 20, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 20, 2021 | Oct 20, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2021 | Oct 20, 2021 | — |
Fire prevention review Fire Department · SFFD | Oct 20, 2021 | Oct 20, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 5, 2021 | Nov 5, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 8, 2021 | Nov 8, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 8, 2021 | Nov 16, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $8,000
| Name | Role | License on permit |
|---|---|---|
| Van Thai Ly Van T. Ly & Associataes | Architect | C25710 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023