48 Stockton St
San Francisco permit 202111082012 · Financial District/South Beach
Change of use retail to office (37,402 sf). new office entrance and service entry. new elevators, elevator lobbies, and basement level bicycle commuter facility. replacement of existing mep systems, screening and new roof system. selective interior demolition to accomodate new use.
- Filed
- Nov 8, 2021
- Issued
- Jul 14, 2022 (8 months after filing)
- Completed
- Mar 15, 2024 (20 months after issuance)
- Review stops
- 16 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 8, 2021 | Nov 9, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 9, 2021 | Jun 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 9, 2021 | Jul 6, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 22, 2021 | Apr 21, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2021 | May 27, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Dec 22, 2021 | Apr 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 22, 2021 | May 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 22, 2021 | Jun 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2021 | Mar 14, 2022 | — |
Public health review Public Health · HEALTH | Dec 22, 2021 | May 9, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 20, 2022 | May 31, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 16, 2022 | Jun 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2022 | Jul 5, 2022 | — |
Public health review Public Health · HEALTH | Jun 16, 2022 | Jun 30, 2022 | — |
Development fee collection Building Inspection · DFCU | Jun 16, 2022 | Jun 16, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 6, 2022 | Jul 14, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $15,750,000
| Name | Role | License on permit |
|---|---|---|
| Benedict John Tranel | Architect | C30466 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026