Scope of work
As written on the permit application.

Remodel kitchen for better layout, including removing existing spiral staircase for more cabinetry/countertops, removing partition from dining room for new peninsula, and closing up hallway access to add storage. addition of small deck and steps to grade near bedroom and a new patio in the backyard.

Timeline
Key dates from the city record.
Filed
Nov 9, 2021
Issued
Aug 15, 2023 (21 months after filing)
Completed
Aug 1, 2024 (12 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 4 departments
Comments issued
None
Put on hold
7 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 25, 2022—

Zoning review

Planning · CP-ZOC

Jan 25, 2023—

Permit Processing Center

Building Inspection · PPC

Aug 7, 2023—

Planning neighborhood notice

Planning · CP-NP

Oct 31, 2022—

Building plan review

Building Inspection · BLDG

May 12, 2023—

Structural plan approval

Building Inspection · PAD-STR

May 15, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Mar 28, 2023—

Street use and mapping

Public Works · DPW-BSM

Feb 1, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 17, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Mar 28, 2023—

Zoning review

Planning · CP-ZOC

Mar 28, 2023—

Street use and mapping

Public Works · DPW-BSM

Mar 29, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 29, 2023—

Building plan review

Building Inspection · BLDG

May 12, 2023—

Zoning review

Planning · CP-ZOC

Apr 25, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 1, 2023—

Street use and mapping

Public Works · DPW-BSM

Aug 3, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 25, 2023—

Zoning review

Planning · CP-ZOC

May 1, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 1, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 1, 2023—

Building plan review

Building Inspection · BLDG

May 12, 2023—

Zoning review

Planning · CP-ZOC

May 17, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 12, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 15, 2023—

Central Permit Bureau

Building Inspection · CPB

Aug 15, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$64,361
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ethan C Andersen

Drafting Cafe Architects

ArchitectC34235
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202111092064 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record