2652 California St
San Francisco permit 202111162539 · Pacific Heights
Horizontal & vertical addition for (n) 2nd dwelling unit. remodel (e) unit w/ (n) stair to (n) deck at (e) roof. (n) passenger elevator. (n) concrete sidewalk. front facade improvements. (n) mep systems. (n) rear yard landscaping, retaining walls & paving.
- Filed
- Nov 16, 2021
- Issued
- Jul 29, 2024 (32 months after filing)
- Completed
- Not completed yet
- Review stops
- 62 stops across 6 departments
- Comments issued
- 19 times, by Building Inspection, Permit Center, Public Works, Public Utilities
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 16, 2021 | Nov 19, 2021 | Administrative |
Zoning review Planning · CP-ZOC | Nov 19, 2021 | Mar 27, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 19, 2021 | May 31, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Nov 8, 2022 | Mar 27, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Mar 27, 2023 | Apr 4, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 27, 2023 | May 15, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2023 | Apr 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2023 | Apr 26, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 5, 2024 | Mar 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 23, 2024 | Mar 4, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 23, 2024 | Feb 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2024 | Mar 14, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2024 | Mar 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 1, 2024 | Mar 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Apr 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 10, 2024 | Apr 12, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 10, 2024 | Apr 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2024 | Apr 16, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2024 | Apr 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2024 | Apr 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 12, 2024 | Apr 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 31, 2024 | Jul 29, 2024 | Administrative |
Addendum 1: Final (foundation, superstructure, t-24)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 12, 2024 | Sep 26, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 17, 2024 | Sep 17, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 17, 2024 | Sep 17, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 20, 2024 | Sep 20, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 11, 2024 | Nov 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 21, 2024 | Nov 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 22, 2024 | Dec 27, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 22, 2024 | Dec 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 22, 2024 | Dec 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 22, 2024 | Nov 27, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2024 | Dec 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 10, 2025 | Apr 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 10, 2025 | Mar 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2025 | Mar 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2025 | Mar 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2025 | Mar 21, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 10, 2025 | In progress | In Progress |
Structural plan approval Building Inspection · PAD-STR | Apr 9, 2025 | Apr 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2025 | Apr 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2025 | Apr 17, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 9, 2025 | Apr 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2025 | May 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 8, 2025 | Aug 13, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2025 | Aug 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 8, 2025 | Aug 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 25, 2025 | Sep 12, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 25, 2025 | Aug 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 25, 2025 | Sep 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2025 | Aug 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 25, 2025 | Aug 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 1, 2025 | Oct 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 1, 2025 | Oct 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2025 | Oct 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 1, 2025 | Oct 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2025 | Oct 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 17, 2025 | Oct 28, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 29, 2025 | Oct 29, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $2,835,800
| Name | Role | License on permit |
|---|---|---|
| Maurice Lombardo Taylor Lombardo Architects | Architect | C26362 |
| Carlos Renan Dominguez Dominguez Associates Llc | Architect | C26949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026