355 12th Av
San Francisco permit 202111172572 · Inner Richmond
Enclose the corner (63 sf per a story) and relocate the existing straight stair case leading from 2nd floor kitchen to the backyard.
- Filed
- Nov 17, 2021
- Issued
- Dec 9, 2024 (37 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 17, 2021 | May 27, 2022 | — |
Zoning review Planning · CP-ZOC | May 27, 2022 | Jan 11, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 27, 2022 | Nov 22, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Oct 16, 2023 | Nov 2, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jan 16, 2024 | Mar 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2024 | Mar 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2024 | Jan 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2024 | Jan 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jan 18, 2024 | Jan 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 23, 2024 | Sep 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2024 | Sep 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2024 | Sep 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 23, 2024 | Aug 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2024 | Aug 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2024 | Sep 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Oct 28, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 11, 2024 | Oct 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 11, 2024 | Oct 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2024 | Oct 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Nov 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2024 | Dec 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $80,000
| Name | Role | License on permit |
|---|---|---|
| Ji Miao Njm Consulting | Engineer | 91104 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025