3660 A Folsom St
San Francisco permit 202111182716 · Bernal Heights
Horizontal first and second floor addition to existing single family residence, convert existing basement to new 1br accessory dwelling unit.
- Filed
- Oct 28, 2025
- Issued
- Jan 23, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 48 stops across 6 departments
- Comments issued
- 12 times, by Public Works, Building Inspection, Planning, Permit Center, Fire Department
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Nov 18, 2021 | Dec 28, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 28, 2021 | Apr 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 28, 2021 | Feb 3, 2022 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 28, 2021 | Dec 30, 2021 | — |
Urban forestry Public Works · DPW-BUF | Dec 28, 2021 | Jul 29, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 28, 2021 | Nov 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 2, 2022 | Oct 27, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Jul 29, 2024 | Jul 29, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jul 1, 2025 | Jul 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2025 | Jul 8, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 1, 2025 | Aug 6, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2025 | Jul 11, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 11, 2025 | Jul 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 15, 2025 | Sep 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 15, 2025 | Sep 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 15, 2025 | Sep 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2025 | Sep 17, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 15, 2025 | Oct 1, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2025 | Sep 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 17, 2025 | Sep 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 7, 2025 | Oct 7, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 20, 2025 | Oct 20, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2025 | Jan 23, 2026 | Administrative |
Addendum 1: Architectural & structural final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2026 | Feb 2, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2026 | Mar 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2026 | Mar 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 3, 2026 | Mar 27, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2026 | Apr 1, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 3, 2026 | Mar 6, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2026 | Mar 11, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 3, 2026 | Apr 10, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2026 | Mar 11, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 3, 2026 | Aug 11, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 27, 2026 | Apr 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 27, 2026 | May 6, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2026 | Apr 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2026 | May 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 4, 2026 | May 7, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 18, 2026 | May 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 18, 2026 | May 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 18, 2026 | May 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2026 | May 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2026 | May 21, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | May 29, 2026 | May 29, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jun 26, 2026 | Aug 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2026 | Sep 1, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $602,000
| Name | Role | License on permit |
|---|---|---|
| Yakuh Django Askew Ya Studio | Architect | C-29776 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2021