65 Raycliff Tr
San Francisco permit 202111182729 · Pacific Heights
Adu conversion of (e) bedroom and study at lower level addition of (n) kitchen that includes (n) appliances, plumbing, millwork & finishes. addition of (n) interior wall and door at (e) mechanical space to create (n) entry at adu. addition of new exterior stair to provide pedestrian access into adu
- Filed
- Nov 18, 2021
- Issued
- Nov 15, 2022 (12 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Nov 18, 2021 | Nov 23, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 23, 2021 | Feb 24, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 23, 2021 | Feb 7, 2022 | — |
Urban forestry Public Works · DPW-BUF | Nov 23, 2021 | Aug 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 23, 2021 | Jul 26, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 9, 2021 | Feb 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2021 | Feb 10, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2022 | Jul 20, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2022 | Apr 5, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2022 | Jul 21, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 2, 2022 | Aug 15, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 4, 2022 | Aug 8, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 4, 2022 | Aug 15, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 4, 2022 | Aug 4, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 4, 2022 | Aug 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 4, 2022 | Aug 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 15, 2022 | Nov 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 16, 2022 | Aug 18, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $58,900
| Name | Role | License on permit |
|---|---|---|
| Towan Kim Brayton Hughes Design Studios | Architect | C32466 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022