730 10th Av
San Francisco permit 202111182752 · Inner Richmond
Convert part of unconditioned garage/storage space at 1/f to conditioned space & addition at rear of structure at 1/f, to include mud room, rec room, guest bedrm suite. n deck at roof of conditioned space & ext. stairs. combined heating & domestic hot water sys, radiant fl heating. n elec heat pump.
- Filed
- Nov 18, 2021
- Issued
- Dec 19, 2022 (13 months after filing)
- Completed
- Sep 12, 2025 (33 months after issuance)
- Review stops
- 18 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 18, 2021 | Dec 9, 2021 | — |
Permit Processing Center Building Inspection · PPC | Dec 9, 2021 | Dec 16, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 10, 2021 | May 23, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Apr 5, 2022 | Apr 6, 2022 | — |
Building plan review Building Inspection · BLDG | May 25, 2022 | Oct 27, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 25, 2022 | Jul 27, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 25, 2022 | May 25, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 25, 2022 | May 26, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 26, 2022 | Jul 27, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2022 | Jul 27, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2022 | Jul 28, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 17, 2022 | Oct 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2022 | Oct 20, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2022 | Oct 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2022 | Oct 19, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2022 | Dec 6, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 6, 2022 | Dec 7, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 16, 2022 | Dec 19, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Karen Anne Eichler Eichler Davies Architecture | Architect | C32415 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022