1417 York St
San Francisco permit 202111192769 · Mission
Single family residential remodel & horizontal addition less than 10' in back yard. (n) master bedroom & bathroom on level 1. remodel (e) kitchen & bathroom on level 2. replace all windows doors & repair (e) stucco. automatic sprinkler throughout bldg under separate permit.
- Filed
- Nov 19, 2021
- Issued
- Oct 9, 2024 (35 months after filing)
- Completed
- Not completed yet
- Review stops
- 38 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Permit Center, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 19, 2021 | Jan 6, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 6, 2022 | May 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 7, 2022 | May 6, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Feb 11, 2022 | Mar 25, 2022 | — |
Building plan review Building Inspection · BLDG | May 9, 2022 | Sep 12, 2022 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 9, 2022 | Aug 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2022 | May 18, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 28, 2023 | Dec 8, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 30, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 28, 2023 | Dec 19, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 28, 2023 | Dec 1, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 26, 2024 | Feb 9, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 26, 2024 | Feb 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2024 | Feb 7, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2024 | Jan 30, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 16, 2024 | Feb 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 29, 2024 | Apr 3, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Mar 29, 2024 | Apr 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 29, 2024 | Apr 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 29, 2024 | May 1, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2024 | Apr 8, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 22, 2024 | Apr 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 8, 2024 | May 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 21, 2024 | Oct 9, 2024 | Administrative |
Addendum 1: Final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 15, 2024 | Dec 5, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2024 | Jan 6, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2024 | Dec 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 6, 2025 | May 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Feb 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2025 | Jan 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2025 | Jan 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2025 | Jan 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 6, 2025 | May 14, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2025 | Mar 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2025 | Mar 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2025 | Apr 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2025 | Mar 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 14, 2025 | May 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $548,257
| Name | Role | License on permit |
|---|---|---|
| Adam Michael Franch Adam Franch Architecture | Architect | C34374 |
| Sean Thomas Condry Stc Design & Engineering | Engineer | 60860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026