1750 Van Ness Av
San Francisco permit 202111232980 · Nob Hill
Erect new 6-story over 1 bsmt, type ib, 40,514 gross sqft bldg for new buddhist temple & accessory bookstore. bsmt lvl of 23,517 sqft for below grade garage w/7 veh. parking, 1 ada, 14 class-1 bike space, storage, mech area. project includes 30 private, no-cost dorm rm for attendees/religious guest.
- Filed
- Nov 23, 2021
- Issued
- Dec 9, 2022 (13 months after filing)
- Completed
- Not completed yet
- Review stops
- 126 stops across 7 departments
- Comments issued
- 13 times, by Fire Department, Public Works, Building Inspection, Permit Center
- Put on hold
- 20 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 23, 2021 | Nov 30, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2021 | Jun 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 30, 2021 | Dec 2, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2022 | Oct 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 11, 2022 | Oct 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 11, 2022 | Jun 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 11, 2022 | Jan 14, 2022 | — |
Public health review Public Health · HEALTH | Jan 11, 2022 | May 18, 2022 | — |
Public health review Public Health · HEALTH | Jan 19, 2022 | Mar 4, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 14, 2022 | Jun 14, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 7, 2022 | Oct 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2022 | Oct 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2022 | Oct 11, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 18, 2022 | Oct 18, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2022 | Oct 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 18, 2022 | Oct 26, 2022 | — |
Public health review Public Health · HEALTH | Oct 31, 2022 | Oct 31, 2022 | — |
Development fee collection Building Inspection · DFCU | Oct 31, 2022 | Nov 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 2, 2022 | Dec 9, 2022 | — |
Addendum 1: Grading, foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2022 | Jan 3, 2023 | — |
Public health review Public Health · HEALTH | Jan 4, 2023 | Mar 29, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 4, 2023 | Jun 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 5, 2023 | Jun 14, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 6, 2023 | Mar 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 6, 2023 | Mar 2, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2023 | Jan 11, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 13, 2023 | May 16, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 14, 2023 | Jun 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2023 | Jun 20, 2023 | — |
Public health review Public Health · HEALTH | Jun 14, 2023 | Jun 16, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 26, 2023 | Jun 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2023 | Jul 10, 2023 | — |
Addendum 2: Architectural, civil, t-24, mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2022 | Jan 3, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 4, 2023 | Apr 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 4, 2023 | May 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 4, 2023 | Jul 26, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 4, 2023 | Sep 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 4, 2023 | Jan 6, 2023 | — |
Public health review Public Health · HEALTH | Jan 4, 2023 | Jan 30, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 4, 2023 | Sep 13, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 3, 2023 | May 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2023 | Jun 5, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 16, 2023 | May 16, 2023 | — |
Building plan review Building Inspection · BLDG | May 17, 2023 | Aug 9, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2023 | Jul 25, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 6, 2023 | Jun 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2023 | Aug 1, 2023 | Approved |
Plumbing plan check Building Inspection · PID-PC | Jul 21, 2023 | Jul 25, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2023 | Jul 25, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 26, 2023 | Jul 26, 2023 | — |
Development fee collection Building Inspection · DFCU | Aug 15, 2023 | Aug 15, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 31, 2023 | Aug 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2023 | Sep 7, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Sep 7, 2023 | Sep 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 7, 2023 | Sep 7, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 7, 2023 | Sep 11, 2023 | Approved |
Plumbing plan check Building Inspection · PID-PC | Sep 7, 2023 | Sep 11, 2023 | Approved |
Public health review Public Health · HEALTH | Sep 7, 2023 | Sep 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 7, 2023 | Sep 8, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2023 | Sep 14, 2023 | Administrative |
Addendum 3: Exterior wall
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 13, 2023 | Dec 13, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 13, 2023 | Feb 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 13, 2023 | Feb 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 13, 2023 | Dec 14, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 13, 2023 | Mar 7, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Feb 20, 2024 | Feb 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 28, 2024 | Feb 29, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 28, 2024 | Mar 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2024 | Mar 14, 2024 | Administrative |
Addendum 4: Sprinkler system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 2, 2023 | Oct 2, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 2, 2023 | Nov 4, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 2, 2023 | Mar 20, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 14, 2023 | Dec 14, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 26, 2024 | Jan 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 26, 2024 | Feb 26, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 12, 2024 | Mar 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2024 | Mar 22, 2024 | Administrative |
Addendum 5: Fire alarm system & 2-way communication system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 13, 2024 | Feb 23, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Feb 16, 2024 | Feb 23, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 23, 2024 | Feb 23, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 23, 2024 | Mar 14, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 23, 2024 | Apr 17, 2024 | — |
Fire prevention review Fire Department · SFFD | Apr 9, 2024 | Apr 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 16, 2024 | Apr 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2024 | Apr 18, 2024 | Administrative |
Addendum 6: Steel stair
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 26, 2023 | Jan 11, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 11, 2024 | Mar 14, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 11, 2024 | Feb 27, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 11, 2024 | Apr 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 29, 2024 | Mar 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2024 | Apr 2, 2024 | Administrative |
Addendum 7: Building maintenance system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 15, 2024 | Mar 22, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 18, 2024 | Mar 18, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 21, 2024 | Mar 21, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Apr 8, 2024 | Apr 15, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 15, 2024 | Apr 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2024 | Apr 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 16, 2024 | Jun 4, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 16, 2024 | May 2, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Apr 16, 2024 | Jun 4, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 2, 2024 | May 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2024 | Jun 7, 2024 | Administrative |
Addendum 8: Photovoltaic system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 21, 2024 | Jul 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2024 | Jul 5, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Jun 26, 2024 | Jun 26, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 27, 2024 | Jun 27, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 2, 2024 | Jul 2, 2024 | Not Applicable |
Zoning review Planning · CP-ZOC | Jul 5, 2024 | Jul 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 5, 2024 | Aug 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 5, 2024 | Jul 15, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jul 5, 2024 | Sep 13, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jul 10, 2024 | Jul 16, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 16, 2024 | Jul 16, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 15, 2024 | Aug 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 30, 2024 | Aug 30, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 10, 2024 | Sep 10, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 10, 2024 | Sep 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2024 | Sep 18, 2024 | Administrative |
Addendum 9: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 19, 2024 | May 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2024 | May 1, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 23, 2024 | Apr 23, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 1, 2024 | May 10, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 1, 2024 | Jun 13, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 21, 2024 | May 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 11, 2024 | Jun 13, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2024 | Jun 14, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $16,000,000
| Name | Role | License on permit |
|---|---|---|
| Clifton K Boswell Skidmore, Ownings & Merrill | Architect | C26963 |
| Mark P Sarkisian Skidmoe Owings & Merrill | Engineer | S4639 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026