744 Rhode Island St
San Francisco permit 202111293185 · Potrero Hill
Add a 3rd fl w/ roof deck. upgrade all structure & foundation to meet/ exceed current code. complete partially excavated 1st fl basement/garage. upgrade m.e.p. to code. increase permeable area of sidewalk. increase area of solar panels & add gray water system. install sprinkler system per nfpa13r.
- Filed
- Nov 29, 2021
- Issued
- Nov 1, 2024 (35 months after filing)
- Completed
- Not completed yet
- Review stops
- 104 stops across 6 departments
- Comments issued
- 23 times, by Building Inspection, Fire Department, Public Works, Public Utilities
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2021 | Nov 29, 2021 | Administrative |
Zoning review Planning · CP-ZOC | Nov 29, 2021 | Jul 12, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 29, 2021 | Sep 17, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Oct 12, 2022 | Jul 12, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 20, 2023 | Aug 22, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 20, 2023 | Aug 15, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Aug 8, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2023 | Jul 27, 2023 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 1, 2023 | Aug 1, 2023 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 8, 2023 | Dec 27, 2023 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Sep 6, 2023 | Sep 11, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Dec 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2023 | Sep 7, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 6, 2023 | Sep 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 12, 2023 | Oct 24, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 27, 2023 | Dec 4, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 27, 2023 | Nov 29, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 27, 2023 | Nov 27, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2023 | Dec 6, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 27, 2023 | Dec 18, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jan 30, 2024 | Feb 15, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 30, 2024 | Feb 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2024 | Feb 2, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 30, 2024 | Feb 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2024 | Feb 22, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 30, 2024 | Jul 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2024 | Feb 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 24, 2024 | Apr 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 26, 2024 | May 1, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 26, 2024 | Apr 29, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 26, 2024 | May 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2024 | May 7, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2024 | May 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 4, 2024 | Jun 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jun 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 4, 2024 | Jun 6, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2024 | Jun 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2024 | Jun 13, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2024 | Jun 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 20, 2024 | Jun 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 20, 2024 | Jun 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 20, 2024 | Jun 20, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 20, 2024 | Jun 21, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2024 | Jul 11, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2024 | Jul 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2024 | Jul 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 1, 2024 | Jul 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2024 | Jul 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2024 | Jul 8, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 1, 2024 | Aug 20, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 20, 2024 | Aug 27, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 20, 2024 | Aug 20, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Aug 20, 2024 | Aug 20, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2024 | Aug 20, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2024 | Aug 21, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2024 | Sep 10, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2024 | Aug 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2024 | Aug 23, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 23, 2024 | Aug 23, 2024 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Aug 23, 2024 | Aug 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 23, 2024 | Sep 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2024 | Sep 12, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Sep 11, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 9, 2024 | Sep 16, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Sep 9, 2024 | Sep 16, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2024 | Sep 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2024 | Nov 1, 2024 | Administrative |
Addendum 1: Foundation, superstructure, t-24 , architecture , mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 1, 2025 | May 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 2, 2025 | May 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2025 | May 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2025 | Jul 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2025 | Jul 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2025 | Jul 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 28, 2025 | Aug 20, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | May 30, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 28, 2025 | Jul 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2025 | Jun 5, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 28, 2025 | Aug 6, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2025 | Jun 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 29, 2026 | May 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2026 | Jun 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2026 | May 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2026 | May 11, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 29, 2026 | May 6, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2026 | May 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 29, 2026 | May 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2026 | May 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 12, 2026 | May 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 12, 2026 | May 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2026 | Jun 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 12, 2026 | May 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 12, 2026 | May 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2026 | May 14, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 19, 2026 | Jun 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2026 | May 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 30, 2026 | Jul 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 30, 2026 | Jul 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 30, 2026 | Jul 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 30, 2026 | Jul 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 30, 2026 | Jul 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 30, 2026 | Jul 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 30, 2026 | Jul 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 3, 2026 | Aug 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2026 | Aug 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Joseph L Powell Powell Architecture | Architect | C31314 |
| Benjamin Pan-Hon Lai Benjamin Lai & Associates | Engineer | 3268 |
| Brendan Forslund Beazley Jon Brody Structural Engineers | Engineer | S5660 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025